0.7 Preview Release Process
This page describes the process for pulling together all of the pieces for the Chandler Desktop 0.7 release.
The
checklist below focuses mostly on process aspect (what happen in which order). It is not a substitute for the
Preview Countdown list.
Members of the Chandler Desktop Release Management team (Philippe, Heikki, Aparna, Sheila), feel free to add things to this process and discuss it during the release meetings.
Release Management Schedule
| What | Owner | Criteria | ETA | Status | Bug# |
| Code Complete | Bug Council | All features in and working (<= 5 bugs per component) | Jul 17th | Done | |
| ZBR | Bug Council | 0 blockers left | Jul 30th | | |
| Build RC | Bear | | ZBR + 0 | | |
| Test RC | Aparna | | ZBR + 4 days | | |
| Approve RC | Aparna | No blocker logged | ZBR + 4 days | | |
| Backing period | Aparna | No blocker shows up | ZBR + 7 days | | |
| Release declared | Release Team | | ZBR + 7 days | | |
| Checksums for downloads | Bear | | ZBR + 8 days | | |
Code Dependent Deliverables
See the
general Preview Code Dependent table.
All of these are done as of 07/22/07.
Non Code Deliverables
See the
general Preview non Code Dependent table.
This is mostly end user documentation and wiki tasks. Includes end user documentation, developers documentation, etc...
Other
See
0.6 Release Management for what we did last time.
--
PhilippeBossut - 23 Jul 2007