OSAF Weekly Status 28 April 2006
This report covers the period from Apr 22-Apr 28 2006 (one week).
Highlights
- Chandler
- Alpha2 bug count going down quickly, some bugs triaged and others fixed
- Feature freeze Monday (May 1) -- wxColumnHeader and Markup bar to land by Monday
- Background sync moved to alpha3
- Cosmo
- Scooby
Design and PM (Sheila)
Progress:
- Chandler
- Alpha3 planning continued and start working on detailed specs (lozenge design, stamping)
- Alpha2 non-code release planning - draft of readme doc.
- 1.0 strategy work - prioritization and prep work on target user.
- Scooby
- Final details for 0.1 release.
- Following 0.2 progress - some design discussions on the list.
Plans:
- Chandler
- 1.0 planning and Alpha3 specs/details
- Scooby
- Support work for 0.2.
- 1.0 planning as part of the target user work.
Application WG (Philippe)
- Progress
- Bug count going down very fast
- All tasks for alpha2 in except for wxColumnHeader integration and Markup bar though both are extremelly close
- Plan
- Team will be focusing on fixing bugs, write functional tests and help others get stuff in alpha2
- wxColumnHeader integration (David) and Markup bar (Reid) to land on Monday
More details available in
AppsMeeting20060427
Platform WG (Katie)
- Progress
- alpha2 bug fixes: email, recurrence, timezone, etc.
- created a branch for background sync work
- after a series of view merging bugs and fixes (recurrence gives it a workout), made decision to rewrite view merging
- background sync moved to alpha3 to incorporate the new view merging, as well as testing after that
- setuptools checked in to Python 2.5 trunk, but backed out after last minute objections
- setuptools improvements to support dynamic choice to build eggs from local source if available (as per list proposal)
- Plans
- regression test i18n features set in Chandler
- writeup of sharing scenarios for testing
- work on dump/reload proposal
More details available at
PlatformMtg20060425
QA, Build and Release (Heikki/Mikeal)
Progress:
- Finished most of the initial Chandler alpha2 feature testing.
- Verified lots of resolved bugs.
- Over the weekend did cosmo automation test writing documentation in preperation for sprint week
Plans:
- Getting ready for sprint week, cosmo 0.3 rc, and chandler alpha2 rc.
Cosmo and Scooby (John)
Progress:
Plans:
IT (Jared)
Progress:
Plans:
Community (Pieter/Ted)
Progress:
- Work on committer policy
- Work on Scooby landing page
- Work on Cosmo landing page
Plans:
- Landing Pages
- Portal Project