This report covers the period from Jan 25 2006 to Jan 31 2006 (one week).

Highlights

  • Progress:
    • Chandler 0.7 design is in progress with lots of participation.
    • Cosmo 0.3 features in development.
    • Scooby 0.1 release packaging work ongoing.
  • Plans:
    • Start writing initial specs for Chandler 0.7; milestone plan for Chandler.
    • Finish up Chandler 0.6.1.

Design and PM (Sheila)

  • Progress:
    • Progress on free-busy/invitations - design session to review proposal.
    • Dashboard design and discussions continued.
    • Review of detail view spec for 0.7.
    • Start domain model discussions.
  • Plans:
    • Chandler: Closure on free-busy/notifications proposal, first draft of spec, screen mockups. Specs for timezone, detail view and markup bar. Summarize current dashboard proposal and suggestions for staging.
    • Scooby: Release work in progress. Revisit schedule to see if we need to move the date or remove some features.
    • Cosmo: Need to send out a writeup of Cosmo screen review for the list.

Application WG (Philippe)

  • Progress:
    • Lots of progress on the Design front. Things are getting clearer for free/busy, invitation workflow. More work on Dashboard needed.
    • Bug triaging moving forward, more to do
    • 0.6.1 bug fixes on target
  • Plan:
    • Continue progress on 0.7 Architecture tasks
    • Review remaining 0.7 bugs, prioritize
    • Start SWAGging bugs
    • Create a Wiki page for "Geek Talk: subjects for Apps meeting (Philippe)

Platform WG (Katie)

  • Progress:
    • 0.6.1 bug fixes
    • sharing proposal
    • zanshin fixes
    • work on eggs and setuptools
    • repository bug fixes (merge bugs, etc.)
  • Plan:
    • Remove libxml2 from zanshin (use elementtree)
    • Preparing PyCon papers
    • 0.7 domain model plan
    • Schema evolution (goals, technical design)
    • 0.7 sharing plan
    • 0.7 calendar and email service plan

QA, Build and Release (Heikki/Aparna)

  • Progress:
    • scooby test automation using jsunit
    • 0.6.1 release testing
    • Debugging functional test failures on Linux
  • Plans:
    • verify 0.6.1 blocker bug fixes
    • scooby test plan
    • discuss cosmo automation strategy

Cosmo and Scooby (Lisa/Bobby)

Progress: Cosmo 0.3 features in development. Scooby 0.1 release packaging work ongoing.

Plans: Cosmo feature development; Scooby finishing, move towards code complete, and help QA ramp up.

IT (Jared)

Progress:

Plans:

Community (Pieter/Ted)

  • Progress:
    • held workshop on internet information person
    • started assembling list of OSU projects
    • decided to move irc to freenode
    • initial draft of governance memo posted
  • Plans:
    • actual move of irc to freenode
    • project list to OSU
    • decide on mailing list renames
Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r7 < r6 < r5 < r4 < r3 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.