| April 18th - April 24th | ||||||||||
| Project : Categories / Higher education | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Pieter Hartsook | Coordinate the logistics for the May Westwood Advisory Council Meeting at U of VA. | In progress | Coordinate the logistics for the May Westwood Advisory Council Meeting at U of VA. WAC meeting May 6 2004 | Completed paperwork for the room reservation under OSAF, coordinated logistics for AV, internet, etc. for the meeting. We should be all set infrastructurewise for the meeting. Purchased an inexpensive 802.11b access point so that we can have wireless access in the room for everyone, and Chao will also take the NEC projector to VA to save the expense of renting one from the hotel AV service. | ||||||
| Project : Categories / Product design | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Brian Skinner | Design docs | In progress | (3) As per Chao's request, serve as driver for the list of next actions from March users & groups meeting? -- coordinate tasks and make sure everything gets done. (N) Get started on the Calendar design doc, if time permits. (+) Also, updated the Design To Do List? | (3) Done. Sent more mail to Andi, Ted, and Lisa. Met with them on Monday. Sent status mail to Chao. (N) Nope. | ||||||
| Brian Skinner | Design meetings | In progress | (1) Meeting on Monday to sort out the terminology and definition issues around "Persona+" and "Sharing Address" (see Repository Terminology). (2) Plan agenda for design meeting Thursday (+) Also attended the Monday repository group meeting. See Lisa's notes: Repository Sharing Meeting 2004/04/19 | (1) Done. See Design Group Meeting 2004/04/19 (2) Met on Tuesday about Processing Items and on Thursday about Exportable Addresses? | ||||||
| Brian Skinner | Template for design docs | In progress | (N) Meet with Mimi to work on doc templates, the Project Overview Table, use case organization, etc. (N) Finish up on design doc page templates, and get Chao and Mimi to sign off on them. Do a little more work on About Page Types? and its sub-pages, so that they have all the features Mitch asked for. (Assign doc type to Interaction Design Spec) (N) Work with Mimi implement the proposals outlined in Design Group Meeting 2004 03 01 (N) Apply templates to a half dozen existing design docs, or as Chao suggests, delegate some of this to Chao and Mimi. (N) Review with Chao and Mimi the proposed changes to the Project Overview Table, and then make the changes. (N) Work with Mimi to get all our Use Cases organized. (N) Work with Mimi to create a page with a diagram that serves as a "map" of the documentation landscape. | (N) Nope, didn't get to any of these tasks, although I did spend some time helping Pieter with making our Page Type Header bars offer RSS links. | ||||||
| Project : Chandler development | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Lisa Dusseault | 0.4 Planning, ongoing | In progress | Review "next steps" in 0.4 planning page | Reviewed status and "next steps" of 0.4 planning page in Services WG (first repeat of a weekly process) | ||||||
| Mark Jaffe | Investigation of Subversion as new SCM tool | In progress | Install svn on oahu server; request assistance from IT for pre-requisites (correct Apache, Berkeley DB.) Setup preliminary repository by import from current CVS | |||||||
| Katie Parlante | Threading snake | In progress | probably won't get to it this week | didn't get to this | ||||||
| Project : Chandler development / Application | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Katie Parlante | 0.4 release planning | In progress | + Meet with John and Jed on Monday, come up with plan for tabbed views, sidebar and summary table view + Read through the latest round of design specs | + Met with John and Jed, plan for the next milestone + Morgen to do sharing ui work instead of calendar + Some design spec reading | ||||||
| Morgen Sagen | Move the launcher programs out of osaf/chandler/Chandler and into the /internal directory | Completed | Move the launcher programs out of osaf/chandler/Chandler and into the /internal directory | I wrote a new-style Makefile to build chandler and chandler_bin and checked it in. Markie will be completing the process. | ||||||
| Morgen Sagen | Get PyCrust? back into Chandler | Not started | Get a menu item back in there to launch PyCrust? interactive shell | |||||||
| Project : Chandler development / Application / Content model | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Lisa Dusseault | Deal with contact content model issues | In progress | Figure out what more issues exist | Made proposal for dealing with importing contact data from other applications (in Journal). Added more tasks to status manager to track other issues. | ||||||
| Lisa Dusseault | Fix content model for calendar items that can have attendees. | Not started | Make a proposal for attendees to be separate items within the calendar item cloud. | |||||||
| Brian Skinner | PIM level Content Model. | In progress | (N) Be available to Katie if I can help her with the task of formalizing the content model for collections. | (N) Yup, talked to Katie a bit and answered a couple questions. | ||||||
| Project : Chandler development / Capplets / Primary / Mail | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Brian Kirsch | Familiarize with Chandler and Email Issues / Requirements | Completed | 1. Evaluate Email Wiki Pages and Wiki Addressing 2. Download and evaluate the Divmod / Twisted email libraries 3. Post an invitation on Design mailing list for 3rd party email suggestions to get feedback from community. 4. Compile and read through Chandler .3 source | Done | ||||||
| Brian Kirsch | Meet with Brian Warner regarding Spam control and Twisted Framework Document meeting off Wiki Email Service Page | Completed | Done | |||||||
| Brian Kirsch | Migrate MailCApplet? data and links to new Service Working Group Email Service Wiki Improve / Update Email Service Page | Completed | Done | |||||||
| Brian Kirsch | Evaluate Quotient / Twisted | In progress | 1.Meet with Anthony Baxter 2. Read through all docs and search web / newsgroups for info on Twisted and webdav / p2p protocols. 3. Create a sample application in Twisted and Quotient to evaluate easy of development, performance, build environment, etc. (This task will carry in to the following week) | |||||||
| Brian Kirsch | Finalize Decision for IMAP Library | In progress | Contact IMAPLib developer Look at Quotient in depth Look at Mail Man Take Stuart's Pop Chandler code and convert to IMAP for testing | |||||||
| Project : Chandler development / Capplets / Third party / Zaobao | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Stuart Parmenter | Check in new feedparser and related unicode changes | Completed | Check in new feedparser and related unicode changes | Done | ||||||
| Project : Chandler development / Framework | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Lisa Dusseault | Define protocol architecture requirements | In progress | Work on use cases with Chao and Brian to actually hook up with workflows. Research various peer-to-peer connector protocols | |||||||
| Lisa Dusseault | Resolve 2-layer addressing plans | In progress | Review namespace skeleton with Mimi. Remove user-facing requirements from spec page. Add character restriction and i18n considerations. Collect and describe (separately) requirements for parcel developers. | Making progress on implementation detail. Ted is working on data model. Reviewed alternate namespace skeleton with Mimi, Brian and Mitch. Made some progress on removing design info from engineering part. | ||||||
| Katie Parlante | Parcels/capplets proposal | In progress | work on proposal | (+) various brainstorming conversations with john and jed, in the context of cpia, I think we now have consensus, ready to write up the plan | ||||||
| Katie Parlante | queries/collections proposal | In progress | work on proposal | (+) conversations with Mitch, Mimi and others, now ready to write up proposal. | ||||||
| Project : Chandler development / Framework / Agent framework | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Stuart Parmenter | Check in new task manager | Completed | Check in new task manager | Done | ||||||
| Project : Chandler development / Framework / CPIA | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| John Anderson | Meet to design block requirements for our next 2 week milestone. | Completed | Identified design problems and came up with solutions. | Done | ||||||
| John Anderson | Meet with Katie and Jed to discuss the definition of a Capplet | Completed | Came to a common understanding of the definition of a Capplet | Done | ||||||
| John Anderson | Move readonly events into schema file | Completed | This has a dependency on the parcel loader. Morgen has decided that the benefits of doing this don't out weigh the disadvantages. So we're not going to do it. | Done | ||||||
| Project : Chandler development / Framework / Parcel framework | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Morgen Sagen | Improve parcel loading framework | In progress | Write a spec based on the proposal. | Delayed due to PTO time (sick child) | ||||||
| Project : Chandler development / Framework / Repository | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Lisa Dusseault | Work related to Chandler ACLs - design, review --? | Not started | Figure out who owns various ACL pieces. Read Capabilities paper. Discuss whether to use WebDAV permissions. Write down how we figured out that principal IDs are going to work as a draft engineering spec. Discuss how item clouds relate to ACLs. | Andi owns ACL implementation (and a subsequent design review). | ||||||
| Project : Chandler development / Framework / Repository / Data model | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Ted Leung | DataModelIssues/Data Model Spec | In progress | Clarify proposal Get started | Proposal clarified and announced. Facilitated meeting on item cloud development Did a little work on a specification document Began updating wiki pages Had several discussions about external addresses Reviewed item cloud code | ||||||
| Andi Vajda | Make data model wonderful | In progress | (You haven't yet entered a plan for this week. Your previous plan has been copied here. Edit this text then click "Save Task"): make data model wonderful | - added Cloud kind to core schema - added Endpoint kind to core schema - first pass implementation of item clouds - added Actor.cloud and ref collection expansion support - checked in first pass at cloud implementation - unsupport using deprecated 'dict' (first through check() enhancement) | ||||||
| Project : Chandler development / Framework / Repository / Persistence | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| John Anderson | Solve the schema evolution problem as well as it was solved using ZODB in the previous design. | Not started | I am going to postpone this task until later, since we have more pressing needs. | |||||||
| Andi Vajda | Revive repository sharing | Completed | complete | Given the number of meetings and discussions regarding sharing I think one can consider the task of 'reviving' sharing complete. A new task is to be added called 'Sharing items between Chandlers' | ||||||
| Project : Chandler development / Framework / Repository / Query | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Ted Leung | Flesh out QueryItem? API | In progress | Start on QueryItem? implementation. | Tried to update to new build. Still having problems. Had several clarifying discussions with Katie | ||||||
| Project : Chandler development / Framework / Security | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Katie Parlante | Review design team's security proposal | Completed | I think this task is out of date by now, marking it completed. | Done | ||||||
| Project : Chandler development / Framework / Sharing/Discovery | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Stuart Parmenter | Set up webdav server to test with | Completed | Set up webdav server to test with | Got webdav working on my home linux box | ||||||
| Stuart Parmenter | Get chandler exporting repository items to WebDAV | In progress | Get chandler exporting repository items to WebDAV | Started working with Greg Stein's davlib.py and got some very simple stuff being published to webdav. | ||||||
| Stuart Parmenter | Read Lisa's WebDAV book and get up to speed on webdav | In progress | Read Lisa's WebDAV book and get up to speed on webdav | About 4/5 of the way through the book | ||||||
| Project : Chandler development / Framework / Third party / wxPython | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Robin Dunn | Chapter reivews and editing for the wxPython book. | In progress | Chapter reivews and editing for the wxPython book. | nothing new this week | ||||||
| Robin Dunn | Work on adding more docstrings for the SWIG gererated functions and methods. | In progress | Work on adding more docstrings for the SWIG gererated functions and methods. | worked on other aspects of the ref docs instead | ||||||
| Robin Dunn | Work on tools to extract the docstrings and detatiled docs from the SWIG XML output and put it into a simplified format that can be used for creating online HTML (or other formats) for wxPython reference documentation. | In progress | Write a tool (coordinating with community volunteers) that uses the new XML format to build input for a standard Python documenter tool. Evaluate Riaan's conversion script | I decided that instead of generating something that epydoc can grok that I would teach epydoc some new tricks. I added the ability to filter what in the module will be seen by epydoc, to be able to extract the function signatures from the docstring if they are there instead of using introspection, and the ability to treat anything in all as if it were defined in the local module instead of wherever it may have been imported from. | ||||||
| Project : Chandler development / Meta projects / Releases | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Katie Parlante | 0.4 release planning | In progress | + Meet with John and Jed on Monday, come up with plan for tabbed views, sidebar and summary table view + Read through the latest round of design specs | + Met with John and Jed, plan for the next milestone + Morgen to do sharing ui work instead of calendar + Some design spec reading | ||||||
| Andi Vajda | Improve build | In progress | improve build | - did full windows release build - added GCJ_HOME detection to new build - added openssl-0.9.7d.tar.gz to sources tarball for new build | ||||||
| Project : Chandler development / Tools | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Mark Jaffe | Investigation of Subversion as new SCM tool | In progress | Install svn on oahu server; request assistance from IT for pre-requisites (correct Apache, Berkeley DB.) Setup preliminary repository by import from current CVS | |||||||
| Project : Chandler development / Tools / CVS | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Mark Jaffe | Investigation of Subversion as new SCM tool | In progress | Install svn on oahu server; request assistance from IT for pre-requisites (correct Apache, Berkeley DB.) Setup preliminary repository by import from current CVS | |||||||
| Project : Chandler development / Tools / HardHat | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Mark Jaffe | Investigation of Subversion as new SCM tool | In progress | Install svn on oahu server; request assistance from IT for pre-requisites (correct Apache, Berkeley DB.) Setup preliminary repository by import from current CVS | |||||||
| Project : Community | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Mitchell Baker | Help all working groups define a reasonable set of community related goals for the 0.4 release. | In progress | Assist working groups as requested. | No requests so far. Spend some time with Ted brainstorming on good steps for the future; how to help make distributed development more of the norm. Also spend time figuring out how to arrange the Community Working Group to help with this; decided to "narrowcast" our focus on a few potential key people rather than "broadcast" efforts aimed for a broader group, since it's so early in the Chandler cycle and difficult for that broader group to participate. | ||||||
| Mitchell Baker | Attend Community Working Group meeting | In progress | Attend if possible, discuss CWG focus. | Unable to attend as was at Internet2. | ||||||
| Mitchell Baker | Attend Management Committee and All Hands Meetings; create and distribute notes from each. | In progress | Attend meetings. Create and distribute notes. | Missed the management committee due to travel. Done for the All Hands. Esther is now handling the distributing of All Hands notes, may begin the drafting work as well. | ||||||
| Mitchell Baker | Figure out what needs to be done to comply with government regulations once Chandler has encryption technology included. | In progress | No plans for this week. | Nothing done here, as per the week's plan. | ||||||
| Mitchell Baker | Periodic discussions of community related topics at the All Hands and Management Committee meetings. | In progress | Defer discussion until next week, until CWG had made its way through its refocusing effort. | Deferred a a week. | ||||||
| Mitchell Baker | Evaluate the use of one or more Common Cause licenses for the content of the OSAF wikis. | In progress | Review Pieter's summary. | Waiting for Pieter's summary. | ||||||
| Pieter Hartsook | Figure out how to record and present videos of Chandler demos to the community. | In progress | Figure out how to record and present videos of Chandler demos to the community. | back-burner this week, but want to have something for the upcoming demo for Chandler UI stuff. | ||||||
| Ted Leung | Fine tune CWG | In progress | Work on course adjustments for CWG | |||||||
| Ducky Sherwood | Add metrics for rank of various wiki pages and RSS hits. | Completed | Done | |||||||
| Ducky Sherwood | Negotiate, announce, moderate, and post metrics for Office Hours. | Completed | Done | |||||||
| Ducky Sherwood | Set up cron jobs for metrics | Completed | Set up cron jobs for metrics | Done | ||||||
| Ducky Sherwood | Explore real-time collaborative editing tools. | In progress | Looked at VNC (which doesn't seem to allow more than one viewer per server, at least w/Mac client). Looked at jEdit (which has cumbersome "I'm editing now" lock). | |||||||
| Ducky Sherwood | Explore shtoom. | In progress | (You haven't yet entered a plan for this week. Your previous plan has been copied here. Edit this text then click "Save Task"): Explore shtoom. | Waiting to get my headset back. | ||||||
| Ducky Sherwood | Review about ten open source projects' "developer portals" to see what their "quick hit" pages look like; make a similar quick-hit page for Chandler/OSAF. | In progress | Started looking at pages. | |||||||
| Ducky Sherwood | Track various CVS metrics, including lines of code added, to qualitative community metrics. | In progress | Track various CVS metrics, including lines of code added, to qualitative community metrics. | Waiting for bonsai access... | ||||||
| Ducky Sherwood | Make web interface to those metric scripts that can be run as a normal user. | Not started | Need to check with Mitchell on priority for this. She figures its worth 1-3 days. | |||||||
| Project : Community / Wiki | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Pieter Hartsook | Figure out how to create a standard wiki expression using variables that could be inserted unaltered into every wiki page to provide a custom RSS feed for that page Topic. | In progress | Figure out how to create a standard wiki expression using variables that could be inserted unaltered into every wiki page to provide a custom RSS feed for that page Topic. | With help from Brian Skinner and volunteer Grant Bow all the Chandler Wiki pages using page headers have a link to a validated RSS feed for that topic (that page and all other pages that refer to that page by topic name). The creator or editor of the page doesn't have to do anything but select a pagetype in the page form and add the variable at the head of the Wiki page. Everyhing else is automatic. Here's the documentation RSS variable wiki-fu to make this work. The next step suggested by the wiki-masters on #twiki is to replace the variables with %INCLUDE statements to reduce the load overhead for each page. Plan to work on that next week. | ||||||
| Brian Skinner | Library Project | In progress | (4) draft proposed list of steps and then get feedback and/or approval to move forward (N) If time permits, work my way through other tasks on the Library Project? to-do list. | (4) Done. Drafted Library Project Proposal 2004/04/19, posted it to the dev list, and hosted a discussion about it during the Wednesday IRC office hour (followed by a long phone call with Ducky talking about the pros and cons of having IRC office hours, and how that fits with OSAF goals) (N) Nope. | ||||||
| Project : IETF | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Lisa Dusseault | Standardize PATCH proposal to make WebDAV writes higher performance | Not started | Revise PATCH - publish 01 draft | Draft revised and ready to go but not quite submitted. | ||||||
| Project : Marketing / Events | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Mitchell Baker | Prepare outline for presentation to the NWACC Annual Retreat, June 16-18. | Not started | Make progress. | Didn't make progress. | ||||||
| Pieter Hartsook | Coordinate the logistics for the May Westwood Advisory Council Meeting at U of VA. | In progress | Coordinate the logistics for the May Westwood Advisory Council Meeting at U of VA. WAC meeting May 6 2004 | Completed paperwork for the room reservation under OSAF, coordinated logistics for AV, internet, etc. for the meeting. We should be all set infrastructurewise for the meeting. Purchased an inexpensive 802.11b access point so that we can have wireless access in the room for everyone, and Chao will also take the NEC projector to VA to save the expense of renting one from the hotel AV service. | ||||||
| Project : Marketing / Marcomm | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Pieter Hartsook | Figure out how to create a standard wiki expression using variables that could be inserted unaltered into every wiki page to provide a custom RSS feed for that page Topic. | In progress | Figure out how to create a standard wiki expression using variables that could be inserted unaltered into every wiki page to provide a custom RSS feed for that page Topic. | With help from Brian Skinner and volunteer Grant Bow all the Chandler Wiki pages using page headers have a link to a validated RSS feed for that topic (that page and all other pages that refer to that page by topic name). The creator or editor of the page doesn't have to do anything but select a pagetype in the page form and add the variable at the head of the Wiki page. Everyhing else is automatic. Here's the documentation RSS variable wiki-fu to make this work. The next step suggested by the wiki-masters on #twiki is to replace the variables with %INCLUDE statements to reduce the load overhead for each page. Plan to work on that next week. | ||||||
| Pieter Hartsook | Respond to email inquiries and requests, keep the website updated, post status manager reports, etc. | In progress | Respond to email inquiries and requests, keep the website updated, post status manager reports, new hire info, etc. Monitor and respond to Email that comes to info @ osafoundation.org as well as some of the mail that is sent to Mitch. | on-going task | ||||||
| Pieter Hartsook | Figure out how to record and present videos of Chandler demos to the community. | In progress | Figure out how to record and present videos of Chandler demos to the community. | back-burner this week, but want to have something for the upcoming demo for Chandler UI stuff. | ||||||
| Project : OSA Foundation / Facilities | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Pieter Hartsook | select and purchase projector screen for large conference room within 2 weeks | Completed | select and purchase projector screen for large conference room within 2 weeks | * Item 1: Da-Lite Model B 69x92" High Contrast Matte White - $197
| ||||||
| Project : OSA Foundation / HR | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Mitchell Baker | Work with Ducky to make the best use of her time in the community arena | In progress | Define tasks for this week, and for the upcoming months. | Done. Also discussed plans for the CWG in general. | ||||||
| Ted Leung | Work on reviews | Completed | Work on reviews | |||||||
| Brian Skinner | performance reviews | In progress | (5) Fill out more performance review forms (three down, three to go). | (5) Nope, didn't get to it. | ||||||
| Project : OSA Foundation / System administration | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Jurgen Botz | Zero Spam | In progress | - Implement greylisting as a subroutine in mimedefang - Implement DSPAM - provide UI for DSPAM training | - no work this week | ||||||
| Project : OSA Foundation / System administration / Server | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Jurgen Botz | Big file server for backups | In progress | - put system into service | - lots of progress and setbacks... - turns out thing still has interrupt problems with 3 controllers and all 8 drives - to solve this, switched to K-Mart mainboard | ||||||
| Jurgen Botz | Install nutch and use to index OSAF sites (including twiki) | In progress | - try newer snapshot | - played with new snapshots | ||||||
| Jurgen Botz | New Moveable Type install... - update moveable type and move to kahuna - do a separate install elsewhere for Mitch's personal blog | In progress | - to complete this week | - played with moveable type to understand what's involved. it's pretty simple, actually | ||||||
| Project : OSA Foundation / System administration / Status manager | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| Morgen Sagen | Have status manager indicate how recently a task has been modified | Completed | Either not do automatic task carryover, or timestamp plan entries, or... | I now have a beta version that doesn't carry over plans to future weeks. Mitch needs to approve it. | ||||||
| Project : To be assigned | ||||||||||
| Person | Goal | Status | Planned this week | Progress this week | ||||||
| John Anderson | Build all of Chandler on each of the tree platforms | Completed | I spent quite a bit of time getting the external builds to complete on each of the platforms. | Done | ||||||
| John Anderson | Work with the UI design group to specify the 0.4 UI well enough so we can build it. | Completed | Done | |||||||
| Mitchell Baker | Prepare for April 20 talk at Internet2 | In progress | Go. Present. | Done. Presentation was focused on what the Mozilla project has to offer beyond a end-user browser application. Talk was well received. Ken an Michael Gettes to follow up. | ||||||
| Mitchell Baker | Work with other KKIE members to develop a shared value statement. | In progress | Schedule review of doc by Mitch. | Not done, still need to schedule. | ||||||
| Jurgen Botz | Anonymous email to Mitch | In progress | - complete Monday 4/19 | - came up with simple effective design - hacked up quick prototype | ||||||
| Robin Dunn | Work with other wx-dev folks to stabalize the recent changes regarding making wxADJUST_MINSIZE the default behavior in sizers, and also the window view attributes (font, colors, etc.) defaults and inheritance. | Completed | Decide what to do about items whose minsize is smaller then their bestsize. Double-check the view attribute changes. | Made the sizers check minsize separately from bestsize. | ||||||
| Robin Dunn | Coordinate with Will Sadkin on integrating a new version of his MaskedEditControls? modules | Completed | Coordinate with Will Sadkin on integrating a new version of his MaskedEditControls? modules | Done and also some bugs fixed | ||||||
| Robin Dunn | Create a module that can morph the 2.4 DC classes into something more compatible with the 2.5 DC classes for people that want to try and keep their code working on both versions. | Completed | Done | |||||||
| Robin Dunn | Coordinate with contributors working on an enhanced implementaion of the pupsub module. | Not started | Coordinate with contributors working on an enhanced implementaion of the pupsub module. | |||||||
| Robin Dunn | Fix wxGTK2 wxMessageDialog problems. (I think they are due to wxMessageDialog now using a native API and so calling other methods on it cause problems.) | Not started | Fix wxGTK2 wxMessageDialog problems. (I think they are due to wxMessageDialog now using a native API and so calling other methods on it cause problems.) | |||||||
| Jeffrey Harris | Create functionality to import/export Chandler data to standard formats, with special emphasis on Outlook. | In progress | Change Contact Schema based on Lisa's input. Finish mapping data structure from an XML file instead of a a Python structure. Start writing iCalendar import code. Update Contact unit tests (really, I'm going to do this!). | Held off on changing schema for Mitch to choose what should be added. Finished a working implementation of XML mapping description, debugging took longer than I thought, of course. Also, listened in on a meeting about Item Clouds. Had a good phone conversation with Lisa about exportable addresses and offering access to repository data through different protocols. | ||||||
| Jeffrey Harris | Let people know my schedule for the week. I'm in Central (GMT -6:00). | In progress | Monday - All day Tuesday - Morning Wednesday - Afternoon Thurdsay - other work Friday - All day | |||||||
| Mitch Kapor | intergroup issues coordination | In progress | continue to focus on: "item clouds" sharing and replication external addresses wxWidgets development by core wx team, by OSAF staff | came up with use cases and user considerations to present at RWG 4.19 lots of progress, see my Staff Notes | ||||||
| Mitch Kapor | performance reviews | Not started | accomplish something here with 3rd one in my queue | slipped again! Ugh! | ||||||
| Heikki Toivonen | Vacation. Back on Tuesday 27th. | In progress | Vacation. Back on Tuesday 27th. | |||||||