Operations group meeting notes for 2007-03-27

Attendees: Heikki, Sheila, Katie, Philippe, Aparna, Jared, Ted

  • Interns
    • Philippe has been reviewing intern applications. Some current counts of applications were given, but were missed by this note-taker.
    • Summer of code: The shortened Google timeframe for applications may be contributing to not-entirely focused applications.

  • Reviews
    • We had originally said to put off review until after Preview.
    • With Preview slipping, it's not realistic to keep putting it off.
    • We're looking at end of April, end of May.
    • Process includes:
      • Pick peer reviewers
      • Write peer reviews
      • Self reviews
      • Manager reviews
      • In-person reviews
    • Want to avoid scheduling review steps during times when teams have project deliverables.
    • Cosmo team during late April, early May will be otherwise occupied with release.
    • PPD prefer to due earlier, like end of April. Same for QA.

  • Lakiba ran some interviews with people within OSAF late last year.
    • She recently provided summary feedback to Katie.
    • Themes observed included decision making and process. Katie will be summarizing for discussion at the ops-wg level.

  • Conferences, travel, and budget
    • Launch party
      • We've been planning a launch party. The idea includes bringing remote people on-site.
      • The party was underbudgeted, as number of people off-site has increased, and per-person budget was low.
      • Philippe will review our budget actuals to see how much money is left.
    • Conferences
      • Original plan included: 6 people for Calconnect, 2 Etech, 1 WWDC, 1 CSG, 4 OSCON, 2 ApacheCon?.
      • QA is looking at the Google testing conference.
      • Conferences fall into at least 2 different categories: OSAF promotion, and professional development
      • CSG has both a May and September date coming up. September seems a better time to participate, so as to have Chandler products already released.
      • Google conference is fine for QA to participate, but travel and lodging won't be covered by OSAF during this year of increased OSAF promotion.

  • Preview
    • Going to blog about schedule adjustment
    • We'll work to move to a more regular blogging schedule. We'll work to blog at milestones, and track them on the Preview countdown meeting.

  • Staff meeting demos
Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r1 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.