Operations group meeting notes for 2007-03-27
Attendees: Heikki, Sheila, Katie, Philippe, Aparna, Jared, Ted
- Interns
- Philippe has been reviewing intern applications. Some current counts of applications were given, but were missed by this note-taker.
- Summer of code: The shortened Google timeframe for applications may be contributing to not-entirely focused applications.
- Reviews
- We had originally said to put off review until after Preview.
- With Preview slipping, it's not realistic to keep putting it off.
- We're looking at end of April, end of May.
- Process includes:
- Pick peer reviewers
- Write peer reviews
- Self reviews
- Manager reviews
- In-person reviews
- Want to avoid scheduling review steps during times when teams have project deliverables.
- Cosmo team during late April, early May will be otherwise occupied with release.
- PPD prefer to due earlier, like end of April. Same for QA.
- Lakiba ran some interviews with people within OSAF late last year.
- She recently provided summary feedback to Katie.
- Themes observed included decision making and process. Katie will be summarizing for discussion at the ops-wg level.
- Conferences, travel, and budget
- Launch party
- We've been planning a launch party. The idea includes bringing remote people on-site.
- The party was underbudgeted, as number of people off-site has increased, and per-person budget was low.
- Philippe will review our budget actuals to see how much money is left.
- Conferences
- Original plan included: 6 people for Calconnect, 2 Etech, 1 WWDC, 1 CSG, 4 OSCON, 2 ApacheCon?.
- QA is looking at the Google testing conference.
- Conferences fall into at least 2 different categories: OSAF promotion, and professional development
- CSG has both a May and September date coming up. September seems a better time to participate, so as to have Chandler products already released.
- Google conference is fine for QA to participate, but travel and lodging won't be covered by OSAF during this year of increased OSAF promotion.
- Preview
- Going to blog about schedule adjustment
- We'll work to move to a more regular blogging schedule. We'll work to blog at milestones, and track them on the Preview countdown meeting.