PPD Meeting Oct 23th, 2006

Agenda

  • Wiki
    • Proposal write-up
    • Requirements
  • Design sessions
    • This week - recurring events discussion
    • Next week - Dashboard review with Cosmo folks - whoville is not available
    • Cosmo meeting agenda for next week
  • Mitch presentations - Nov 10th, Nov 15th
  • Issues?
    • Cosmo
    • Chandler
  • Branding - meetings

Notes

Wiki

  • Priscilla and Jared will put together a proposal and send to Ted, Katie, Sheila and Mimi for review.

Design Sessions

  • Tues Oct 31st - discussion for recurrence and the table issues
    • Should we include the Cosmo folks?
    • Probably not for this meeting since it will be very detailed.
    • Priss will try to schedule a smaller conference room if available since it's a small group.
  • Tues Nov 7th - Dashboard 101
    • Need to book a room for this since Whoville will be booked.
    • Mimi will demo a shared dashboard.
    • Sheila will walk-through the spec and various important sections.
    • In addition to Mimi demoing the dashboard, we can take the items that people come with...show how it would go in the dashboard.
    • This and the demo will take 20 min.
    • Sheila will prepare a proposal for spec discussion.
    • Will log questions people have about how this works with Cosmo - talk about in a separate discussion.
    • Set the context of the discussion at the beginning of the meeting.
  • Follow-up meeting to talk about Cosmo dashboard proposal - adhoc discussions

Mitch Presentations

  • Two 90 min meetings scheduled

  • Nov 10th - Chandler desktop Preview plan
    • Talk about - what's in Preview
    • Top priorities and focus
    • Plan for Alpha5 and Alpha6 - tenets/goals
    • What is being defered
    • Top risks/issues
    • Trial run of presentation next week

  • Nov 15th - Cosmo UI Preview plan
    • Talk about what is Cosmo Preview
    • What's in/what's out
    • What users are going to be able to do
    • What defered/puntable
    • Top risks/issues/uncertainties
    • Meet with Ted/Priscilla to talk about specifics

Issues

  • Chandler
    • eng meeting last thursday
    • decided to test Chandler with Cosmo 0.5 when it's ready and patch as necessary
    • same process for Cosmo 0.5
  • Cosmo
    • bug council today
    • found a few sharing issues
    • hoping to get the release out this week
    • Priss nervous about schedule for Cosmo - Nov and Preview is not far away

Branding

  • Priscilla needs to sit down with Pieter and discuss
  • Priss will coordinate with Pieter on the agenda and meeting schedule
  • Keep the meetings brief and coordinated
  • Need to be aggressive about the schedule
  • Priss will send out the agenda before hand
  • Should we send it to the PR list?
  • Sets some deadlines

Status

Sheila

  • Progress
    • Updated Email spec
    • Updated dashboard spec
    • Alpha4 dogfooding - helping to track down lots of problems
    • Bug councils
    • Schedule Preview plan reviews with Mitch
    • Planning for design discussions with Cosmo folks
    • Alpha5 spec/design discussions - started to schedule
    • Branding - more naming activities
  • Plans
    • Recurring events in table discussion
    • Design list summary
    • Work in Preview presentations for Mitch
    • Branding - naming workshops, craft position statement
    • Dogfooding Chandler, more Alpha4 bug triage
    • Non-code deliverables for Chandler Alpha4
    • More planning for Cosmo dashboard review

Priscilla

  • Progress

    • Helping out with Pieter on braning exercises.
    • Unified URL - Review the mock ups Mimi did and work in new proposals which include Admin UI/Cosmo UI merge.

  • Plans
    • 0.6 spec written as much as I can for now. Waiting for final estimates from Ted and will review final features for 0.6.
    • General item support wireframes - Planning to review with developers for Thursday if we have time.
    • Work out where to put the Admin console links from Cosmo. Need to sketch out ideas first then go over with Mimi.
    • Finalize on on Cosmo 0.6 with Ted and present to the team. Update information on the wiki.
    • Still working through the punchlist of non-developement tasks, sent it to the list and updating my progress. This item will be done when 0.5 is officially released.
    • Cosmo landing pages - working with Pieter on upcoming 0.5 launch for landing pages.
    • Wiki/portal project - To start working with Jared and creating the wiki fresh from a new server.

Mimi

  • *Progress
    • Branding: Concept map for Prosocial + Time
    • Iterating on Dashboard spec with Sheila
    • Dogfooding * bug loggin
    • Cosmo Magic URL workflow storyboards, take 2

  • Plans
    • Work with Pieter on pro-social concept map
    • Wittle down words for productive
    • Preparing for Tuesday's design session on Dashboard, Recurrence and Triage workflow
    • Organize ItemsStampingCommunications
    • Strawperson proposal for a simplified Dashboard in Cosmo UI
    • Prepare Alpha 4 Dashboard demo and use case exercise

-- SheilaMooney - 30 Oct 2006

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r9 < r8 < r7 < r6 < r5 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.