PPD Meeting Oct 23th, 2006

Agenda

  • Release update
    • Chandler 0.7Alpha4
    • Cosmo 0.5
  • Design session this week
  • Wiki
  • Design issues for the list
  • Any other presentations we should be doing
  • Vacation

Notes

  • Release update
    • Chandler 0.7Alpha4
    • Cosmo 0.5
  • Design session this week
  • Wiki
  • Design issues for the list
  • Any other presentations we should be doing
  • Vacation

Status

Release update

  • Chandler 0.7Alpha4
    • Mimi dogfooding and logging bugs for the dashboard
    • Appears more stable
    • Priscilla and Sheila dogfooding as well - Sheila will start logging bugs for email
  • Cosmo 0.5
    • Branched but still waiting for recurrence work to finish
    • Current release estimate is Nov 1

Design session this week

  • Magic URL discussion
  • Decide by Friday what next week's session will be

Wiki

  • Jared is going to be setting up a server
  • Problem using the branch that we have
  • Made sense to do this because it was going to be difficult using what we have
  • Timeline for this? Priscilla will be meeting with Jared tomorrow and send an update
  • Sheila will think about doing a new home page for PPD (Mimi has time to do some work on this)

Design list

  • Sheila will do weekly summary
  • Not much traffic due to bug fixing for both teams.

Any other presentations we should be doing

  • Cosmo people in town the week of Nov 8th
    • Dashboard presentations
    • Scoping table view of more than just events
    • Sit down with Matthew to go over UI issues in detail

Cosmo

  • Some of the admin UI, regular users might want to get out at this functionality
  • Prisiclla and Mimi will talk more on Wed about this.

Branding

* Katie: Is there supposed be a weekly branding meeting? * We will discuss this at today's branding meeting at 3:00pm. * Seems like we need to come back to stuff * Met about position statements - talked about what we like/didn't like.

Vacation

  • Both Mimi and Sheila will be on vacation the end of Nov, beg of Dec

Sheila

  • Progress
    • Review of email spec
    • Alpha4 dogfooding - helping to track down lots of problems
    • Bug councils
    • Met with Katie and Philippe to do resource planning for Alpha5
    • Worked with Ted and Priscilla on next steps for Cosmo stickie plan and possible design sessions for Nov 8th week (Cosmo folks in town).
    • Branding - naming workshop
  • Plans
    • Update email spec
    • Schedule discussions for sharing, recurring events in table
    • Design list summary
    • Design sessions for Cosmo 0.5(magic url) and Chandler Alpha5 (TBD)
    • Participaing in branding meetings/activities
    • Dogfooding Chandler, more Alpha4 bug triage

Priscilla

  • Progress
    • Cosmo 0.5 relesae notes. First draft written. Having Ted review before sending them to Pieter.
    • Cosmo 0.5 spec update and wiki update are done for now.
    • 0.6 spec written as much as I can for now. Waiting for final estimates from Ted and will review final features for 0.6.
    • Started working on the wiki project end of last week. Made a decision to wait for new wiki server and work with Jared on a regular basis start on the wiki project.

  • Plans
    • Unified URL - Planning to review with developers for design session Tuesday.
    • General item support wireframes - Planning to review with developers for Thursday if we have time.
    • Work out where to put the Admin console links from Cosmo. Need to sketch out ideas first then go over with Mimi.
    • Finalize on on Cosmo 0.6 with Ted and present to the team. Update information on the wiki.
    • Still working through the punchlist of non-developement tasks, sent it to the list and updating my progress. This item will be done when 0.5 is officially released.
    • Cosmo landing pages - working with Pieter on upcoming 0.5 launch for landing pages.
    • Wiki/portal project - To start working with Jared and creating the wiki fresh from a new server.

Mimi

  • Progress
    • Dogfooding and logging bugs
    • Branding
      • Created a concept map for word brainstorm around the concept productive
    • Target Users
      • Completed write-ups for Target User Descriptions
      • Pulled together images for Target Users and present them with Priss at 1019 staff meeting
    • Pulling together more wiki areas, specifically:

  • Plans * More wiki areas: ItemsStampingCommunications * Target Users: Tweak target users and make them presentable as non-code deliverables for Preview

-- SheilaMooney - 23 Oct 2006

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r11 < r10 < r9 < r8 < r7 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.