Chandler Engineering Meeting, Thursday February 1st 2007

Present: Heikki, Jared, Sheila, Katie, Ted, Aparna, Bear, Morgen, Philippe

0.7alpha5 Progress

  • Recurrence branch landed
  • Bugzilla dogfoodable flag: we're reverting the decision, suppress that flag and instead use the "blocker" value in "severity"
  • EIM
    • Lots of sharing code is changing: serialization, networking, magic URL
    • Jeffrey working on the translator from recurring event to EIM
    • Brian not blocked on Edit/Update (Morgen delivered the API)
    • PJE working on Conflict Management
    • 2 weeks of work before we are complete on Chandler, then we'll need a good week of testing, then we'll be able to migrate some dogfooders.
    • Biggest risk: Cosmo interop, this will drive the Cosmo 0.6.1 realease, completion of code of this will be called "Integration complete"
    • EIM Migration plan: users will have to manually unpublish from the old URL scheme to the new magic URL(s) scheme
  • Dump and Reload: can't be started before EIM/Sharing's done, we don't have a SWAG on that yet. This could be hold off the rest for "feature completion"
  • Conflict resolution and Edit/Update: Blocked by the availability of an API from PJE
  • Triage status: We had a design session on it this week and simplified the scenarios we'll cover for Preview (Mimi emailed the list with decisions). Should be completed by mid February
  • Dashboard on track for mid February completion
  • Search: one more cycle of discussion but converging very fast
  • Performance: need to have people from Apps working with Andi to make progress

0.7alpha5 Schedule

  • At least 5 weeks from Feature Complete (2 weeks for EIM + 1 week of testing + 2 weeks for Dump and Reload)
  • That means that our schedule is moving 3 weeks in the future
  • When EIM is landed and tested, Cosmo 0.6.1 schedule can be set, the first RC of it will be an "Integration Complete" milestone
  • After FC, we'll need a period of 4 weeks for perf work, design tweaks and debug before we can hit Code Complete
  • We'll then enter the pure debug phase that will lead to Release Candidate

Cosmo migration testing and privacy concerns

  • Need to explain better to users what a migration is all about
  • Need to write better Term of service, include provision for admin access
  • Develop a script to extract a set of data for testing (though we'll still need to run full migration tests on the whole set from time to time before doing migrations)

QA

  • Which version of Chandler do we certify Cosmo 0.6 against? We need to certify alpha4 because it's more stable. We can do some testing with alpha5 though.
  • Interop Scenarios: Aparna to send an email to explain how people can help

Other

We decided to have this meeting weekly starting now till Preview.

-- PhilippeBossut - 01 Feb 2007

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r4 < r3 < r2 < r1 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.