Apps team SWAG: 40 days to get to alpha5 CC/FC, makes us hit mid february for CC/Feature complete, add 6 weeks for debug/stabilization to that and we get to end of March
Suggestion: cut alpha6 and do a cycle of pure debug/stabilization and performance
EIM will be finished by then
We need to get some stuff reeled in alpha5:
Dump and Reload
Installers
Other end game features might have to be migrated to alpha5
Take some cut/keep decision on big items:
Conflict management? *Edit/Update?
We need to get PPD input here (Sheila in vacation this week) before we make such a decision -> report the decision to Dec. 21st (next Eng meeting)
Concern with having one less cycle to make adjustment
Mitigation: we'll need to get people to test alpha5 checkpoint when we get to CC/FC
We need to be very clear on what CC/FC and the various milestones in the end game means