Chandler Engineering Meeting - November 16th, 2006
Alpha4
Triage of untargetted bugs
Found 1 blocking and moved 2 others to alpha4
Need to fix those before doing a new checkpoint and wait another 2 days before RC
Earliest RC then will be Tuesday
Alpha5 and Alpha6 timeline (15 min)
Latest SWAG from Apps team shows 50 days of solid work before we get to Code Complete for alpha5
That pushes alpha5 CC to the end of January for the Apps team
On the Platform team, EIM won't be staged as initially planned, we'll go directly to the morse code plan. This makes EIM availability depending on Cosmo 0.6.
What about splitting alpha5? This plan was only considered if we want to get Esther to try things out early. We don't think this is realistic now. It takes a lot of cycles from QA and Engineering to help her so we'd prefer to have her work on a very stable alpha4. This idea of a short alpha5 is then moot.
What can we do to solidify the plan?
Need to proceed with implementation with EIM before a more solid plan can be presented.
Apps team done with the break down on Bugzilla and mapping with PPD plan so more bug scrubbing/prioritization is the way to go.
Having John working on evaluating Search.
Test plan (15 min)
Aparna talk about what we have today, what's missing and how to get there.
0.6 had a test plan but it hasn't been updated since then.
Aparna is planning to write one for alpha5. Will work with Mimi on getting up with scenarios.