Chandler Engineering Meeting - November 16th, 2006

Alpha4

  • Triage of untargetted bugs
  • Found 1 blocking and moved 2 others to alpha4
  • Need to fix those before doing a new checkpoint and wait another 2 days before RC
  • Earliest RC then will be Tuesday

Alpha5 and Alpha6 timeline (15 min)

  • Latest SWAG from Apps team shows 50 days of solid work before we get to Code Complete for alpha5
  • That pushes alpha5 CC to the end of January for the Apps team
  • On the Platform team, EIM won't be staged as initially planned, we'll go directly to the morse code plan. This makes EIM availability depending on Cosmo 0.6.
  • What about splitting alpha5? This plan was only considered if we want to get Esther to try things out early. We don't think this is realistic now. It takes a lot of cycles from QA and Engineering to help her so we'd prefer to have her work on a very stable alpha4. This idea of a short alpha5 is then moot.
  • What can we do to solidify the plan?
    • Need to proceed with implementation with EIM before a more solid plan can be presented.
    • Apps team done with the break down on Bugzilla and mapping with PPD plan so more bug scrubbing/prioritization is the way to go.
    • Having John working on evaluating Search.

Test plan (15 min)

  • Aparna talk about what we have today, what's missing and how to get there.
  • 0.6 had a test plan but it hasn't been updated since then.
  • Aparna is planning to write one for alpha5. Will work with Mimi on getting up with scenarios.

-- PhilippeBossut - 16 Nov 2006

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r2 < r1 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.