Philippe completed an exhaustive review of all the remaining tasks and bugs for the apps team.
He has determined that with OSCON and vacation time, we will require an extra period of 3 weeks to complete all the 0.6 functionality.
The proposal is to have an additional milestone rather than extending Milestone 5 which is scheduled for August 24th.
Milestone 6 would be targetted for Sept 14th and the release moved 3 weeks to Nov 2nd.
Need to create a new item for 0.6.06 in bugzilla.
Heikki will send an email to dev with the new dates and update the milestone page.
IRC QA Session
Focus on testing the calendar.
Keep with default as Pilikia for now since we don't want to broadcast the use for Cosmo QA.
Default Chandler Sharing Server
Talk to Jared about using something other than Pilikia as the default server.
Until Morgen gets the changes to the accounts UI we should have a default account setup with a username and password (like pilikia). Sheila will talk to Jared about this.
Tracking Tasks in Bugzilla
Katie asks - what do we think about using bugzilla to track everybody's tasks?
Andi had requested some kind of patch that allows you to reply via email.
Bugzilla is used in opensource projects, accessible to people.
Need to figure out how to get buy-in from the rest of the team.
Philippe will talk to some of the team to get feedback on this. We will also discuss this with Lisa when she returns from Europe.
We are tracking apps tasks, calendar service project and i18n tasks in there right now.
Katie will look at adding in the developer platform tasks - the ones that we have defined enough to schedule.
Do we need to upgrade bugzilla to a new version?
We will have a bigger discussion about this at the end of 0.6.