Backend
a Model - done
b Cosmo2RPC - 2 days
c RPC2Cosmo - 3 days
Front End
d Model - 2 days
e Conduits - 3 days
f Update UI Code for service layer- 1 wk
g Use Stamp meta - 3 days
Topics
h Create topics - 2 days
i Service layer integration - 1 day
j UI Integration - 1 wk each B & T (parallel)
k Cruft cleanup - 2 days
Worst case - 5w 3d
s 1 2 3 4 5
----|----|----|----|----|
B b|c |d|h| g |j |k|
T e |f |ij |k|
Optimized - 4w 3d
--