Cosmo Planning Meeting

Notes

  • Would we consider changing strategies - is this an option
    • Mimi wanted to understand the range of what we are considering
  • Look at strategy pieces for Preview
    • Put something in front of people
    • Show different stuff
    • Alignment with desktop
  • Schedule point of view
    • Originally risky to get the dashboard done, before we slipped
    • Don't know how long the dashboard will take
    • Might be some dogfood feedback to consider
    • Way the timeline plays out - not sure if we will have time to do more than that
  • Focus on dogfood feedback
  • Scoping the minimum dashboard work
    • In order to do this - Ted will need some more time for backend design (should be this week)
    • Isolate all the minimal dashboard pieces
  • Non-dashboard features - we could consider Jared support stuff

  • What we are hearing
    • No big change in strategy
    • Dashboard beyond back-end work could be a reality
    • Possible dogfood bugs but we already knew this - not a lot of stuff identified yet

  • Need have some list of bugzilla tasks that make up the following...
    • Dogfood bugs we have identified today
    • Previously logged bugs and small tasks for 0.7
    • All the tasks associated with the minimal dashboard

  • What do we need in order to do this...
    • Need to have a negotiation around dogfood feedback - triage session
    • Pull out the minimal dashboard tasks and add to bugzilla
    • Ted need to create the associated back-end tasks.

  • Next actions:
    • Triage the dogfood bugs - first pass from PPD based on priorities (Priscilla)
    • Second iteration would be with the developers to swag what's left in 0.7 (Priscilla will schedule when we are done part 1)
    • Add all the current UI tasks for minimal dashboard into bugzilla assigned to 0.7 (Priscilla)
    • Add the back-end tasks for dashboard into bugzilla (Ted)
    • Swag the tasks (Ted)
    • Other stuff in the 0.7 bucket - deferred from 0.6 (bug council task - this week?)
    • Tasks/work items for code related branding changes (PPD)
      • Sheila did initial inventory, Priscilla will review this and enter all items into bugzilla referencing the super bug
    • Draft the step by step workflows for Cosmo that relate to testing the 0.6.1 code (Priscilla)
    • Look at and comment on the following threads
      • More fun with items in multiple collections - need to read thread and comments
      • Travis thread - about the forgot password

-- SheilaMooney - 13 Mar 2007

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r1 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.