Cosmo Engineering Meeting 5 Jul 2007

Agenda

  • Status update
  • Cosmo 0.7 coordination and priorities
  • Branding implementation issue
  • Hub ToS?
  • Post launch response cycle times

Notes

  • Matthew is the most at risk with 65 bugs, but genreally people are feeling good about their bug counts
  • Adam hopes to have all of the old windmill tests working again by Monday 7/9
  • Mikeal needs to do feedservice tests - He will catch up with Brian Moseley regarding docs for the feed service
  • Post launch maintenance discussion
    • Have maintenance branch and clear ownership of bug triage and branch release management
    • data migration issues seem the riskiest under a quick cycle model
    • What is the threshold for bugs going into a quick release?
    • Maybe having a release on a fixed day of the week is the most sensible - if people miss the train, they can always catch the next one.
  • Mikeal to summarize the Cosmo bug council

Status

Ted

  • Progress
    • Reprioritized bugs to match PPD priorities, also triaged engineering/developer bugs
    • Cosmo 0.7 release stuff
  • Plan
    • Focus team attention on Cosmo 0.7 P1 and P2 bugs
    • Meet with Sheila to cut bugs in anticipation of code complete
    • Work out open issues - licence compliance and e-mail activation features
    • Wiki gardening
    • HelpUs? project

Brian

  • Progress
    • completed feed service features
  • Plan
    • finish feed service spec
    • remaining 0.7 bugs
    • begin planning 0.7.1

Randy

  • Progress
    • 0.7 bugs
    • 0.7 performance testing on lab.osaf.us
  • Plan
    • 0.7 bugs
    • continue performance testing

Bobby

  • Progress
    • feature complete yay!
  • Plan
    • finish remaining 0.7 bugs

Matthew

  • Progress
    • Finished features, knocked out most P1s
  • Plan
    • Kill as many P2s and P3s as I can

Bear

  • Progress
  • Plan

Jared

  • Progress
    • Metrics
    • Three Cosmo release meetings
    • Terms of service start
  • Plans
    • 0.6.1.1 release checklist
    • 0.7 release checklist
    • Big server install
    • Hub integration into wiki

Travis

  • Progress
    • Rebranding
    • Dojo build system hiccups
  • Plans
    • Finish off rebranding and rebranding related cleanup
    • TOS link

-- TedLeung - 03 Jul 2007

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r9 < r8 < r7 < r6 < r5 | More topic actions
 
Open Source Applications Foundation
Except where otherwise noted, this site and its content are licensed by OSAF under an Creative Commons License, Attribution Only 3.0.
See list of page contributors for attributions.