This is a snapshot of the
CurrentCombinedStatus as of Mon Dec 27 07:00:01 2004
Current Combined Status
This page consolidates the status of all the different projects.
0.4.03 milestone
- WxPythonProject?: widgets 2.5.3 (David) waiting for check in
- WxPythonProject?: swig integration (David) ready to go with 2.5.3 build
- CpiaFramework?: printing review (Jed) major printing bugs fixed
- CpiaFramework?: mini calendar design (Jed) done
- CpiaFramework?: first pass at view delegation (John) done
- CpiaFramework?: first pass at attribute editor framework (Donn) done
- CpiaFramework?: improved layout (Bryan) done
- DetailViewProject?: reminders (Bryan) done
- DeveloperPlatformProject?: concrete plan (Katie) done
- CalendarBlocksProject?: calendar design/review (Katie) not done
Plan for 0.4.04 milestone
- WxPythonProject?: native header strategy (David)
- CpiaFramework?: review for printing and mini calendar (Jed)
- CpiaFramework?: SWIG and check in mini-calendar (Jed)
- CpiaFramework?: detail view using view delegation and attribute editor framework (Donn/Bryan/John)
- DeveloperPlatformProject?: zaobao content model update (Katie)
- CalendarBlocksProject?: calendar design/review, calendar view navigation (day-week) (Katie)
Status for milestone 0.4.03:
- Heikki: M2Crypto Done but bug related to mail code
- Heikki: read ACL RFC; research existing ACL models In Progress
- Brian: Finish unit tests and code reviews for WakeupCaller: Done
- Brian: Design discussions on email attachments In progress
- Brian: design discussions notifications Significant progress
- Morgen: Have a plan for fitting Chandler schema to Projects.WebDAV data model Significant progress
- Jeffrey: Get RRULES integrated In progress (more work than expected)
- Jeffrey: Do external object wrapper In progress
- Jeffrey: Get VObject into build Not done
- Jeffrey: talk to Morgen about putting iCalendar on server Done
- Aparna: Work on smoke test instructions integration into bugzilla In Progress
- Mike: Checkin installer code
- windows: Done
- linux/RPM: Done (prototype)
- osx: Pending
Plans for milestone 0.4.04: (21 December)
- Mike: OSX installer checked in
- Mike: linux/rpm installer deal with repository directory
- Aparna: one more update on smoke test instructions
- Brian: Proposal for item query/notifications
- Brian: email "guinea pig" code for item query/notifications
- Brian: Work with Ken on i18n
- Brian: Progress on email attachments design discussions
- Heikki: Twisted integration in M2Crypto
- Heikki: Choose library to add ACL support to
- Heikki: Figure out the API we need to create to support ACLs
- Morgen: tbd
- Jeffrey: More triage on RRULEs stuff (what not to implement)
- Jeffrey: prototype of importing very simple iCal files into repository
- Jeffrey: Get VObject into build done but making makefile work
Bugzilla status by person (shows only tasks that have been entered in Bugzilla):
| Task name/info | Status | Milestone |
| Query support for item collections/sharing ~2T (High) | In Progress | |
| Performance ~4A + ~2T (High) | In progress |
| Version Merging improvements ~3A (High) | In Progress |
| Date/time support in data model ~2T (Med) | Not started |
| Deletion/memory ~1A (Med) | Not started |
| pinning | Done | |
| cloud deletion | Not started |
| Data model API review: what is the public API? ~2T (Med) | Not started |
Design (from DesignToDoList?)
Build (from BuildProject?)
Plans for 0.4 Integration Point A
| Goal | Status |
| Prepare presentation and demo for OSCON 2004 | done |
Plans for Milestone 0.3.21
Plans for 0.4 Integration Point B
Plans for 0.4 Release
| Goal | Status |
| Prepare presentation and demo for Web 2 conference | not started |
| Prepare presentation and demo for EDUCAUSE 2004 | not started |
Cross-project status
EngineeringIssues doesn't yet have status by milestones, but might someday.
We don't have a good status page for IT, but see
EngineeringRequestsForIT?.
--
DuckySherwood? - 06 Jul 2004