This is a snapshot of the CurrentCombinedStatus as of Mon Sep 20 09:49:58 2004

Current Combined Status

This page consolidates the status of all the different projects.


Apps (from ApplicationProject)

Plans for 0.3.24 Integration Point B

  • WxPythonProject: wxWidgets transition (David) not done -- want to get in by Thursday
  • WxPythonProject: 100% CPU bug (David) not done
  • SharingUIProject?: tie up loose ends, Projects.WebDAV account preferences (Morgen) done
  • ParcelManager: Data/schema warnings (Morgen) postponing until .5
  • CpiaFramework: Mac toolbar fixes in build (Jed and David) waiting on wxWidgets transition
  • CpiaFramework: wx.Grid fixes in build (Jed and David) waiting on wxWidgets transition
  • CpiaFramework: event handling improvements (Donn) done
  • ApplicationChromeProject: feature polish, tie up loose ends (Jed) waiting on wxWidgets transition
  • ItemCollections: Kind filtering (John) not done, waiting on stuart accepting fix
  • CpiaFramework: Attribute renderer support for Jed and Donn (John) done
  • DetailViewProject: email Send and catch errors, Projects.ItemCollection detail view (Donn) done
  • CalendarBlocksProject: check in calendar blocks to spec (Katie) done (not yet reviewed)
  • other: Fedora core 2 working with vmware (John) done

Plans for 0.3.25 Feature Freeze

Planning to not do in .4

Reviews

  • Morgen's sharing ui code (Morgen to schedule)
  • Katie's calendar/collection canvas (Katie to schedule)
  • Donn's notification to main view (Donn to schedule)
  • John (and others) attribute editor/renderer (not ready yet)
  • mail content model (wait for Brian to get back)

Issues

  • Short term owner for mail bugs?
  • Content model for sharing
  • Will item collection fixes be accepted?
  • Team would like clarity on how bugzilla will be used in release process (which fields are relevant)
  • Would be good to have a follow up meeting on sharing (Sheila to schedule)


Services (from ServicesWorkingGroup)

Plan for milestone 0.3.25

  • Build: Milestone build next week will be delayed from Sept 21 to Sept 22 or 23.
  • Build: wxWidgets version upgrade is on a separate branch to minimize effect on other stuff
  • Build: Heikki plans to fix Linux launcher bug and a similar bug for Windows that has a nasty workaround.
  • QA: Aparna to work on script for demos as well as regular bug finding and resolution.
  • Stuart: Fix a couple bugs, improve sharing unit tests
  • Stuart: Code review already done
  • Brian: code reviews when he gets back

Bugzilla status by person (shows only tasks that have been entered in Bugzilla):


Repository (from RepositoryFramework)

Plan 3.24 [9/7]

  • Persistence: Version merging
  • Queries: evaluation engine, use existing repository storage structures (indices?)

0.4 Community Goals

  • One or two people helping with QA for the repository -- confirming bugs, reducing test cases, etc.
  • One or two people working on the repository.
  • Not originally a goal, but spin out pylucene project and add contributers

Plan for 0.4 (3.25) [9/21]


Design (from DesignGroupMilestones)

By Integration Point "B"

  • Complete first draft of production projects for following:
    • Rule builder
    • Dashboard view
    • Universal text entry box
  • Brainstorm and scope search
  • Conduct lightweight (concept and paper prototype) usability tests


Build (from BuildProject?)

0.4 (ZeroPointFour?) Goals

  • wxWidgets 2.5 migration - completed
  • Dependencies don't work in all cases; fix them: (30 Apr) Medium
  • Investigate switching away from CVS (Subversion, Perforce, ...): (21 May) Medium/Large
    • Would obviously affect Bonsai, LXR, maybe other webtools
  • Keep up to date with latest releases of 3rd party libraries: ongoing
  • Try to reduce Chandler's dependancy of slightly modified 3rd party libs - try to get Chandler use the standard libs: (21 May) Medium/Large
  • Automate more of the build and release process
    • Smarter Tinderbox (performance reporting, separate release and debug builds, Bonsai links, ...): (28 May) Medium/Large
    • Automatic checksums on download packages: - completed
  • Keep Tinderbox in green - goal is to have outages last less than 6 hours at a time.
  • And in general managing build & release bug list
  • See also ReleaseEngineeringGoals20040309? meeting notes.
#Projects.ReleaseCommunityGoals
  • Community-related goals:
    • one or two more ports.
      • Rationale: this helps verify we're not doing things that make porting hard. It also allows developers using othe distributions to participate.
      • Steps to encourage: Have a list of past and existing ports. Have easy to find info on wht to do if one needs help.
    • volunteers setting up more tinderboxes running on their machines that would report to our tinderbox which would display the results along with our tinderboxes.
      • Rationale: This allows us to see run thorough build cycles with more options -- release and debug builds, some different options on each, and for each platform.
      • Steps to encourage: get our infrastucture ready to accept data from other tinderboxes, and hopefully make it easy to add tinderboxes. Create a good set of information about why this is valuable, how to set up a tinderbox, how to send the data to us.
    • evaluate build-related feedback from Projects.PyCon? and determine if there are easier or standardized ways that we should incorporate.
    • find one or two people with lots of python build experience to make suggestions about build improvements


Community (from CommunityHome)

Plans for 0.4 Integration Point A

Goal Status
Prepare presentation and demo for OSCON 2004 done

Plans for Milestone 0.3.21

Goal Status
Change copyright notice on wiki and web to Creative Commons 80% done
Create consolidated status report wiki page done
Improve wiki fonts, borders done

Plans for 0.4 Integration Point B

Goal Status
   

Plans for 0.4 Release

Goal Status
Prepare presentation and demo for Web 2 conference not started
Prepare presentation and demo for EDUCAUSE 2004 not started


Cross-project status

EngineeringIssues doesn't yet have status by milestones, but might someday.

We don't have a good status page for IT, but see EngineeringRequestsForIT?.

-- DuckySherwood? - 06 Jul 2004

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r9 < r8 < r7 < r6 < r5 | More topic actions
 